On a hillside above the bay in Santa Ponsa, a family villa is being extended and renovated: a new garage level cut into the rock, a lift from the garage to the top floor, larger living spaces and a rebuilt pool.
Plans from the approved project. Some details changed during the build.
The owners wanted more space and better access on a steep plot: a garage they could drive into, a lift to every floor, a larger open plan living, dining and kitchen space, and four bedrooms with their own bathrooms. The existing pool and terraces were to be rebuilt, and the new rooms wrapped in external insulation for comfort through every season.
I manage the project for the owners, who live abroad, as their project manager and owner's representative. I chose and appointed the builder and the specialist trades, run the site meetings, check the work and every valuation against the technical architect's reviews, keep the budget and send the owners a monthly photo report.
The structure is complete, the roofs are insulated, the pool is refilled and the first fix of the electrics and plumbing is done. Windows go in this winter, followed by floors, finishes and the lift, with completion planned for April 2027.
On site
On a site cut into rock, the ground decides a lot. I am on site through each stage, from the excavation and propping under the existing house to the foundations, the slabs and the services, so problems are caught while they are still easy to fix.
Site photos from January to November 2026.














Checking the work for the owner, so the build stays on time, on budget and to the standard agreed.
Videos play from YouTube. Pressing play loads the video from YouTube, whose privacy policy then applies.